In DR scenario operations are transferred to a remote facility to get the organization back online within recovery time objective (RTO) and recovery point objective (RPO) targets.That is how much risk business is willing to take.
Business case for having DR is Loss of revenue, competitive disadvantage, possible regulatory penalties,Legal costs.
Recovery-Time
Objective (RTO): The time within which systems and
applications must be recovered after an outage. It defines the amount of
downtime that a business can endure and survive. Some examples of RTOs
RTO
of 72 hours:Restore from tapes available at a cold site.
RTO
of 12 hours:Restore from tapes available at a hot site.
RTO
of few hours:Use disk-based backup technology, which gives faster
restore than a tape backup.
RTO
of a few seconds:Cluster production servers with bidirectional
mirroring, enabling the applications to run at both sites simultaneously.
Recovery-Point
Objective (RPO): This is the point-in-time to which systems
and data must be recovered after an outage. It defines the amount of data loss
that a business can endure.
Based
on the RPO, organizations plan for the frequency with which a backup or replica
must be made. Example
RPO
of 24 hours:Backups are created at an offsite tape library every
midnight. The corresponding recovery strategy is to restore data from the set
of last backup tapes.
RPO
of 1 hour: Shipping database logs to the remote site every hour. The
corresponding recovery strategy is to recover the database to the point of the
last log shipment.
RPO
in the order of minutes: Mirroring data asynchronously to a remote
site.
RPO
of zero: Mirroring
data synchronously to a remote site.
Return on Investment
Estimated disaster probability in a given years = 2%
Estimated cost for data loss and downtime per incident = $15 million
Probability ´ cost per incident = $300,000
Average cost of DR solution = $80,000 per year
Cost of Avoidance Savings = $220,000 per year
Ref on ROI:www.Libelle.com
Return on Investment
Estimated disaster probability in a given years = 2%
Estimated cost for data loss and downtime per incident = $15 million
Probability ´ cost per incident = $300,000
Average cost of DR solution = $80,000 per year
Cost of Avoidance Savings = $220,000 per year
Ref on ROI:www.Libelle.com
- Plan , Implement and Test Disaster Recovery - First and foremost is having Disaster Recovery plan and effective planning. Goals should be realistic for RTO, RPO and metrics.
- DR and testing should be done at application level not just individual components like Server , Storage and test DR plan at least twice in a year.
- Both failover and failback needs to defined
failover is how from primary site to secondary (DR site) the recovery happens
failback :If Primary site is back to normal after disaster then how the the process of re-synchronizing that data back to the primary location from DR site , halting I/O and application activity once again and cutting back over to the original location.
- Clear defined roles , responsibilities and ownership and proper chain of command, the conditions, criteria which will triggers DR and logistics should be defined and in place before recovery process
- Focus on Business continuance and not just IT, ensuring that people and facilities are available and able to function from a business perspective.
- Identify your most critical applications and data and accordingly prioritize the recovery of critical applications and data.
- Perform Dry Run before actual test to provide additional information regarding any further steps that may need to be included to identify inconsistencies for correction and improvements and other appropriate adjustments and fine tuning the DR plan.
- Change management process needs to be in place to account for any
changes in Production site are propagated to DR site as well.
- Automate the Recovery process as much as possible.
- Virtualise the applications and systems for simplifying the DR
4 comments:
Great post. I heard my parents talking about getting a disaster recovery plan after the hurricane hit earlier this week. I have been doing research to get a little more knowledge, that is how I came across this post. Thanks for sharing, it has been very helpful.
Really Great Post. Thanks for sharing
Disaster Recovery
Great Blog! Thank you so much for sharing this information. You can keep in touch with them via an Accounts Receivable toll-free number +44 20 3627 1872. To have more support, you can visit our site:- Accounts Receivable
Really this is very good article and please find out the related info Accounts Receivable Management Solutions
Post a Comment